Retail Installation Specialists

Project Description

Tesco Frozen Product Presenters

tesco-adinstall

Project Brief

Our brief was to install pushers and t-rails to all shelves holding frozen products in the frozen cabinets, throughout the Tesco estate. We were also required to survey all sites prior to the installations to confirm the data supplied and kit required for each site.

Our Approach

Five pallets of kit on average were needed for each site. Over 40 individual components available, which required ordering specifically for each chiller at every site. Each team was dealing with and installing, on average, over 15,000 components per week.

 

All data was transmitted directly from store and made available via our unique real time web portal. Daily reports were sent to the client summarising the stores completed and the ongoing work schedule was discussed regularly via conference calls.

 

All of our fitters were CSCS accredited and carried risk assessments and a method statement (RAMS) to ensure we met all of our health and safety obligations.

Project Date

Oct 2014 – March 2015

Timeframe

50 working days (10 weeks) with up to 74 staff working each week throughout the rollout.

Compliance

All stores to be attended within the timescale provided by the client for both the surveys and the installations. Target compliance of 100% was achieved.

Related Projects

Interested in this Project?

Fill out our form and we will get back to you.

Back to Top

Enjoying this blog? Find us on social media!

Twitter
Facebook
Google+
LinkedIn
YouTube
Pinterest
INSTAGRAM
Follow by Email