Project Brief

The objective was to de-merchandise existing Games World mods in the Gaming area of Tesco stores and to re-planogram with new shelving and products to a specific layout.

Our Approach

We had to book in with stores at least 48 hours before the planned install date.

 

On site pre and post installation pictures were collected along with site data and signature capture from duty/store manager.

 

All data was transmitted direct from store and made available via our unique real time web portal.

 

Daily reports sent to the client summarising stores completed and schedules along with daily conference calls throughout the installations.

Project Date

Feb to Mar 2016

Timeframe

Work was completed out of hours with over 220 stores attended in a 20 night period.

Compliance

All sites were attended within the time frame. All fitters were CSCS accredited along with production of RAMS to ensure we met all of our health and safety obligations.

Interested in this Project?

Fill out our form and we will get back to you.

Back to Top

Enjoying this blog? Find us on social media!

Twitter
Facebook
Google+
LinkedIn
YouTube
Pinterest
INSTAGRAM
Follow by Email